- Concrete pouring at level 24 is ongoing.
- Curtain wall installation from level 4 up to at level 9 completed.
- Corridor and demising wall framing are ongoing on level 4, 5, 6, and 7.
- Porcelain cladding installation completed up to level 9 of the north elevation.
- HVAC installation is ongoing from level 2 upwards.
- Electrical wire pulling in progress at level 22.
- Permanent lights installation at stair A & B from ground floor up to level 9 is ongoing.
- Stair railing installation up to level 20 is ongoing.